P-401 is a pay item.
The circular numbers its own items. The letter is the family. The paragraphs keep that item number.
Airport construction specifications on federally assisted work start from FAA Advisory Circular 150/5370-10. The project edits that circular, and special provisions can rewrite the item again.
401-2.3. Asphalt binder shall conform to ASTM D6373 Performance Grade (PG) 76-22. SP-3
401-3.3. No asphalt mixture shall be placed until an acceptable mix design has been submitted to the RPR for review and accepted in writing.
401-3.4. RAP shall not be used. Tech spec
The circular numbers its own items. The letter is the family. The paragraphs keep that item number.
Brackets are filled in the project book. A conflicting special provision governs the paragraph it rewrites.
The check runs on the governing text. The finding cites the paragraph and the sheet.
Advisory Circular 150/5370-10 is the FAA’s standard specifications for construction of airports. Edition 150/5370-10H is the one the FAA lists as active. The consolidated PDF on the FAA site includes the published errata.
Paragraph 1 limits the subject to materials and methods: general provisions, earthwork, flexible base courses, rigid base courses, flexible surface courses, rigid pavement, fencing, drainage, turf, and lighting installation. Paragraph 3 says the circular does not constitute a regulation and is not mandatory. It recommends these practices for construction of pavements and airport development serving aircraft greater than 30,000 pounds (13,600 kg). It contains methods acceptable to the Administrator for compliance with 14 CFR part 139. Use is mandatory for all projects funded under federal grant assistance programs, including the Airport Improvement Program, under Grant Assurance No. 34. It is mandatory, as required by regulation, for Passenger Facility Charge projects, under PFC Assurance #9. For building construction, the general contract provisions apply, together with applicable laws and local building codes.
Paragraph 4 says the standards must be edited to develop construction specifications for the individual federally funded project, by copying the pertinent portions into the contract documents. For airfield pavement projects at non-primary airports serving aircraft less than 60,000 pounds (27216 kg), state highway specifications may be used in states where the state has requested and received FAA approval to use state highway specifications. Modifications to standards requests must meet FAA Order 5300.1. For AIP or PFC projects, or for grant-obligated airports, the contract uses the current contract provisions and the mandatory provisions, including wage, labor, and Disadvantaged Business Enterprise requirements. The AIP Handbook points change orders and supplemental agreements on construction and equipment contracts to the current edition of this circular.
FAA review of plans and specifications for federally funded projects checks that the latest revision of AC 150/5370-10 was used and that modifications were identified, and that modifications to construction standards are documented and approved. The memorandum says modification proposals are handled under Order 5300.1. It also says the review is not a quality control check for the engineer of record, and that comments are not official approval of a modification of standards.
A contract item, under paragraph 10-17, is a specific unit of work for which a price is provided in the contract. The circular gives each item a letter for its family and a number that stays on every paragraph inside it.
Part 1. Definitions, control of work, control of materials, and measurement and payment. These are sections, not pay items.
Part 2. C-100 is the contractor quality control program. C-102 is temporary air and water pollution, soil erosion, and siltation control. C-105 is mobilization. C-110 is the method of estimating percentage of material within specification limits (PWL).
Parts 3 through 9. Part 3 is sitework. P-401, in Part 6, is asphalt mix pavement. P-501, in Part 7, is cement concrete pavement. P-610, in Part 9, is concrete for miscellaneous structures.
Parts 10 through 13. F items are fencing, D items are drainage, T items are turfing, and L items are lighting installation.
Item P-401 sits in Part 6, Flexible Pavements. Paragraph 401-1.1 is pavement courses of mineral aggregate and asphalt binder mixed in a central mixing plant and placed on a prepared base or stabilized course, conforming to the lines, grades, thicknesses, and typical cross-sections shown on the plans. Materials are 401-2. Paragraph 401-2.3 says the asphalt binder shall conform to ASTM D6373 Performance Grade (PG), and it leaves the grade in brackets. Composition is 401-3. Paragraph 401-3.3 says no asphalt mixture shall be placed until an acceptable mix design has been submitted to the RPR for review and accepted in writing. Paragraph 401-3.4 brackets a choice, and one of those brackets is “RAP shall not be used.” Construction methods are 401-4, contractor quality control is 401-5, material acceptance is 401-6, measurement is 401-7, and payment is 401-8. Paragraph 401-6.3 determines percent within limits under Item C-110.
Item P-501 sits in Part 7, Rigid Pavement. Paragraph 501-1.1 is pavement of cement concrete, with or without reinforcement as the published brackets require the engineer to choose, on a prepared underlying surface.
MasterFormat numbers a building book by division and section. P-401 is this circular’s item for asphalt mix pavement, and 401-2.3 is a paragraph inside that item.
Item families, P-401, and P-501 are taken from the consolidated circular. See AC 150/5370-10H and the FAA construction standards index.
Two different acts change the published item. The engineer edits the item into the contract. A special provision or a modification of standards can change it again, and they are not the same approval.
Paragraph 5 is the editing rule. Engineer notes, printed between lines of asterisks, explain options to the engineer and must not remain in the final project documents. Where numbers, words, phrases, or sentences are enclosed in brackets, a choice or modification must be made. Where blank spaces occur in sentences, the appropriate data must be inserted. Where an entire paragraph does not apply, the text is deleted, “Not Used” is entered after the paragraph number, and the paragraphs are not renumbered. Paragraph 7 says the English units govern, and that one unit of measure is selected for the final documents.
Paragraph 50-03 is the conflict rule. The pitfalls section states it in the circular’s order, including the blank at paragraph 50-04. The contract, under paragraph 10-16, includes the general provisions, the technical specifications, the plans, supplemental provisions, standards incorporated by reference, and issued addenda, among the other documents that form it. A review that stops at the bid-day item misses an addendum that is part of the contract. Paragraph 10-15 defines a change order as a written order covering changes in the plans, specifications, or proposal quantities, and establishing the basis of payment and contract time adjustment, if any.
A modification of standards is defined at paragraph 10-35 as any deviation from standard specifications applicable to material and construction methods, in accordance with FAA Order 5300.1. Paragraph 5 requires that approval, in accordance with FAA Order 5100.1, for a deviation needed to accommodate an unusual local condition, and it says adding a new section and/or item requires one. Paragraph 4.c names Order 5300.1 for modifications to standards requests. Order 5300.1 requires a materials request when available materials cannot meet the specification or are at a significantly higher cost, a construction-method or tolerance request when the change saves cost or adds efficiency without sacrificing safety or useful life, and a general-provisions request when the change is required to conform to local laws and regulations. Material and construction modifications are approved for the life of the project. An approved modification cannot be modified. The airport submits a new one. A state standard approved under AC 150/5100-13 may be used for nonprimary airport development without a modification of standards, in the state where that standard was approved.
Each miss below is a rule in the circular, the modification order, or Engineering Brief 106.
The downloaded circular still contains engineer notes and empty brackets. A review that cites those notes is citing instructions to the engineer. Paragraph 10-31 adds a second trap: a reference to a numbered paragraph includes the pertinent general requirements of the entire section, specification item, or cited standard.
A deleted paragraph keeps its original number, with “Not Used” entered after it. A special provision, an errata correction, or another item may still cite that number.
Paragraph 50-03 states the order. Calculated dimensions govern over scaled dimensions. Contract technical specifications govern over the general provisions, the plans, cited standards for materials or testing, and cited advisory circulars. General provisions govern over the plans, those cited standards, and cited advisory circulars. Plans govern over cited standards for materials or testing and cited advisory circulars. If a special provision conflicts with the general provisions or the technical specifications, the special provision governs. Paragraph 50-04 is a blank. The engineer lists the special provisions in their order of precedence. When electronic files and hard copy plans are both used and they conflict, the hard copy plans govern.
The engineer note on P-401 limits that item to the surface course for airfield flexible pavements subject to aircraft loadings of gross weights greater than 30,000 pounds (13,600 kg), within the limits of the pavement designed for full load bearing capacity. It also allows P-401 as a stabilized base course. It allows P-403 as the surface course on small maintenance and repair projects of less than 3000 tons (2720 tonnes). It points P-403 at other courses, including stabilized base, binder, and truing and leveling courses, at pavements designed for aircraft gross weights of 30,000 pounds (13,600 kg) or less, and at roads, shoulder pavements, blast pads, and other pavements not subject to full aircraft loading. The bid documents cannot include both Marshall and gyratory mix design methods. The P-501 note is the surface course for airfield rigid pavements subject to aircraft loadings greater than 30,000 pounds. It says Item P-610 is the concrete for sign bases and other formed concrete structures. It allows state highway material specifications for access roads, perimeter roads, and other pavements at aircraft loading less than or equal to 30,000 pounds, and those specifications must include the material requirements of paragraph 501-2.1 for reactivity.
A filled bracket, or a paragraph marked “Not Used,” is the paragraph 5 edit. It is not, by itself, the modification-of-standards approval.
The engineer note on C-110 says to delete that item in its entirety when P-401, P-501, and/or P-404 are not required. Engineering Brief 106 replaces cement paragraphs in AC 150/5370-10H, including P-501 and P-610, and says using those modifications does not require submitting a formal request for a modification of standards.
Specset handles non-standard specifications as well as MasterFormat. Its general parser follows each document’s own structure. It conforms amendments into the base sections, then reviews submittals and plans against that text.
On an airport book, that structure is the circular’s own item numbering. The frames illustrate a fictional project, Quarry Run Municipal. The binder grades shown there fill brackets in the published item. The circular does not require those grades.
The job mix formula still carries the grade the technical specification filled in. Special Provision SP-3 replaces it. Sheet C-301 calls the surface course Item P-401.
FAA statements cite the documents below. Product statements cite the Specset pages linked in the previous section.
Purpose, application, project editing, item structure, P-401, P-501, and paragraph 50-03.
Lists this edition as active, with the PDF, the Word file, and the errata.
Corrections are incorporated in the consolidated PDF on the FAA site.
FAA index of the circular, part by part, including the current complete AC.
Defines construction and materials standards in AC 150/5370-10 and the modification process.
Points construction and equipment contract changes to the current AC 150/5370-10.
Review guides check the latest AC 150/5370-10 and documented modifications. Comments are not modification approval.
Replaces cement paragraphs in AC 150/5370-10H, including P-501 and P-610.
It is the FAA standard specifications for materials and methods used in airport construction. The links below open the consolidated circular and the section that states when use is mandatory.
The letter is the family and the number is the pay item. P-401 is asphalt mix pavement. P-501 is cement concrete pavement. A paragraph keeps the item number, so the binder lives at 401-2.3.
The engineer copies the needed items into the contract and edits them under paragraph 5. Paragraph 50-03 then ranks a conflicting special provision against the general provisions and the technical specifications.
Filling a bracket is project editing under paragraph 5. A modification of standards is the separate approval for a deviation, or for a new section or item. Engineering Brief 106 states its own exception for the cement paragraphs it replaces.
The usual misses are reading the published circular as the contract, losing which document governs, and treating P-401, P-403, and P-501 as one pavement item.
An airport book keeps the circular’s own item numbers. A person still confirms each finding.
Review specifications and drawings in project-wide context. Return verified conflicts, omissions, and constructability risks with the source open.
Fully automated reviews of mix designs, shop drawings, product data, safety plans, and more against every applicable requirement. The package comes back annotated, the way a project engineer would return it.
Compare two plan sets, or two revisions of one sheet. Every change comes back matched by sheet, classified by what it touches, and shown beside the drawing, clouded or not.
Send the edited circular, the special provisions, and the plans.